Grenfell Tower Industry Response Group

Further to AMM 137-17, AMM 141-17 and AMM 145 -17, BRE has published the third set of results from its large scale ‘systems tests’, assessing the fire safety of whole buildings. The third test was of a wall cladding system consisting of ACM cladding with fire retardant polyethylene filler (Category 2) with PIR foam insulation, with fire breaks and cavity barriers in place. 

This AMM gives the results of this fire test together with the Government’s Expert Panel’s advice.  A number of reports and advice to owners and landlords have been issued and this AMM lists these reports and provides links to where the reports/advice etc can be obtained.

 

Dr David Moore
Director of Engineering
BCSA

Email: David.Moore@steelconstruction.org